Project times

Record times directly on projects or on the tasks of the project and evaluate them in the times tab

Lucas Bauche avatar
Written by Lucas Bauche
Updated over a week ago

Where do I see all the times for the project?

There are two ways to view all times of a project:

  1. Go to the project and open the Times tab

  2. Go to the Time reports and filter by your project

View all project times

The Times tab of your project lists all the times that have been tracked on the project (or the project's tasks) so far.

Running times, which have been started with the timer but not yet stopped, are not yet displayed here.

Above the list of all times, you will find a summary of the project times, divided by their status with regard to accounting.

The big button Create report or invoice takes you to the time reports, where you can build more detailed reports and export the times of the project or forward them to your invoice tool.

Can I edit the times in a project all at once?

Yes and no. Unfortunately, this is not possible within the Times tab in your project. There, you can currently only edit the times individually. However, if you jump to the time reports, you have the possibility to select several or all times (via the checkboxes on the left side) and edit them at once.

Did this answer your question?